Ash Basin. DTE Energy

"It has been a pleasure seeing James’ role expand over the project, as his experience and performance warrants. His attention to detail and willingness to learn and grow will be a very valuable asset to DeMaria as his career continues forward."

Project Details

After completing Phase I ,& II, DeMaria was hired by DTE to complete the 2012 Ash Basin Piping Extension project at the DTE Monroe Power Plant. The project scope included the extension of the existing ash piping.

Work Included:

  • New gravel base with geo grid
  • Steel basket supports
  • 4 new runs of 12″ steel ash pipe