Dynomometer Test Cell, Robert Bosch Corporation
Robert Bosch Corporation recently hired DeMaria to upgrade a dynomometer test cell at their Farmington Hills research and technology headquarters.
DeMaria removed the exterior face of the building so construction could be performed from the outside, thus eliminating any disruption to operations in the adjacent interior space of the building.
The underground dynomometer cell was demolished and old dynomometer and air handlers removed. A new concrete cell was built and a new dynomometer installed with new air-handling units, span gas and electrical support equipment. |
|
Project Statistics: |
Cost: |
$664,000 |
Size: |
6,000 sf |
Location: |
Farmington Hills , MI |
Type: |
Renovation / Upgrade |
A/E: |
Harley Ellis Devereaux |
| Delivery: |
Design / Build |
|
|
Project Highlights: |
New vehicle dynomometer |
Two floors |
Design / build approach |
|
|
|
|
|
|
|
|
|
|
|
|
|