Multi-phase Approach  
 
DeMaria implemented a plan that cut two months off the schedule.
 

DeMaria's Health Care Group specializes in construction management, design/build, preconstruction and general contracting services for hospital, medical, laboratory and pharmaceutical clients. Projects range in size from $50,000 to $50,000,000.

Emergency Room Renovations at the Main Campus, Henry Ford Health System

ER renovations can be complicated to perform. They require phasing and contingency planning for when unexpected emergencies in the ER demand contractors leave the surrounding site. Dust and debris must be isolated from patients. The daily routine of doctors, nurses and paramedics must not be severely disrupted.

For these reasons, Henry Ford Health System hired DeMaria to renovate their Emergency Room at their main campus in Detroit. Originally a five-phase project, DeMaria reworked and implemented a three-phase plan that cut two months off of the original schedule, minimized disruptions to Hospital staff, safeguarded patients and protected sensitive medical equipment in the renovated areas.

Project Statistics:

Cost:

$5,300,000

Size:

35,000 sf

Location:

Detroit, MI

Type:

Multi-phase Renovation

A/E:

Albert Kahn Associates

Delivery:

Construction Management at Risk, GMP

Project Highlights:

Triage renovation

Cat #1 station replacement

ER entry area

Pediatric waiting area

Pediatric exam room and walk-in entrance

Upgrade toilets and corridors

Family waiting renovation

Cat #3 waiting area

Office renovation

Lobby renovation

Demolition of existing lobby

Temporary lobby w/ security desk

New registration area

New CT room

New vetra sound room

New casting room

New OB room